Tips and Tricks: Work offline from Project Server

There are a number of reasons why you might want to work offline from Project Server. One, you might want to work on a project while flying across the country (but don’t take your eyes off the instrument panel). Two, the network you are using goes down unexpectedly while you’re are in the middle of…

2

Wrangling with the Timeline

The new Timeline in Project 2010 has become an very popular way to present Project information quickly and attractively. Problem is, you can get a little carried away putting all your tasks on the Timeline, and then have trouble selecting only a few tasks to copy into another program, like PowerPoint or Word. Here is…

1

Tips and Tricks: Deleting summary tasks

One nice thing about summary tasks is that changes to them get reflected (or “rolled down”) to their subtasks. This is fine if you want to move summary tasks around, because all the subtasks move with them. But if you want to delete a summary task, then all the subtasks (and any subtasks under those…

2

Tips and Tricks for Project Show filtered tasks with other tasks

Sometimes, when filtering tasks, wouldn’t it be great if you could see filtered tasks with all the tasks, at the same time? Maybe you want to view filtered tasks within the context of all tasks. For example, Knowing which tasks have deadlines and which don’t can help you prioritize tasks by deciding, say, where to…

8

Tips and Tricks: Changing Constraints Back to Normal

Now you’ve done it. You created a number of tasks in Project 2007 using start dates that you entered manually. Or maybe someone handed you a schedule with many “Must Start On” constraints applied to tasks. Unless you have a good reason to use non-default constraints or manually entered dates on tasks, it is best…

1

Tips and Tricks: Modify the baseline in Project 2007

Change is inevitable. Adding new tasks to a project that has already been approved and baselined can be troublesome—to you and stakeholders. But don’t fret. You don’t need to set a new baseline to take into account the new tasks. Just update the old baseline. To modify the baseline that has already been set, do…

2

Back to Basics: Reporting your status

Here’s the scenario: you’re a team member assigned to some tasks, and (surprise surprise) your manager would like you to provide a status update. What’s more is he wants it done through Project Web Access. You panic a little, maybe break out into cold sweats, can’t sleep a wink, yada yada. Well first of all,…

2

Back to Basics: Let’s talk about the critical path…

The critical path…sounds pretty intimidating doesn’t it? Like some secret passageway to getting your project done on time that only highly experienced project managers could ever possibly identify. And certainly those experienced project managers are the only ones who could actually stick to the path and get things done as planned. It’s not really as…

1

Buffer, downtime, and productivity

Maybe it’s because I’ve been swamped this week while the sun’s been shining here in the beautiful Pacific Northwest, but I’ve been doing some thinking about buffer, downtime, and productivity. I don’t think it’s a secret that projects have a tendency to come in late sometimes. Things come up, bad stuff happens, tasks are delayed…not…

5

Hiding, showing, adding, removing, inserting, etc…oh, and DONUTS

On Office Online, we’ve got this one article, currently called, “Hide or show a column (remove or add a column).” It’s a fine article, but, to be frank, the feature can be a bit confusing, so the feedback we typically get on it is pretty bad. Lots of frustrated comments, low ratings, the whole bit….