Back to Basics: Understanding task dependencies

In most cases, the tasks in a project are related to each other, and the relationships between them drive the schedule for the project. The relationships between the tasks are called "dependencies." In Microsoft Office Project, you can create dependencies between tasks in the same project, and between tasks in different projects.

What kinds of task dependencies are available?

Project offers four kinds of task dependencies: finish-to-start, start-to-start, finish-to-finish, and start-to-finish.

First, let's talk about finish-to-start (FS) dependencies. This is the most common type of dependency and is the default type of dependency that Project uses. In a finish-to-start dependency, the second task in the relationship can't begin until the first task finishes. So, for example, if you were planning a project to make a wedding cake, you might use a finish-to-start dependency between the "Bake cake" and "Decorate cake" tasks. When the "Bake cake" task is finished, the "Decorate cake" task begins.

FS

Start-to-start (SS) dependencies are used when the second task in the relationship can't begin until after the first task in the relationship begins. Start-to-start dependencies don't require that both tasks start at the same time. They simply require that the first task has begun, in order for the second task to begin. Going back to the wedding cake example, let's say you had planned to make the icing for the cake while the cake is baking in the oven. You can't start making the icing until the cake has started baking, so you might use a start-to-start dependency between the "Bake cake" and "Make icing" tasks.

SS

If one of your tasks can't finish until another one finishes, you can use a finish-to-finish (FF) dependency between them. Finish-to-finish dependencies don't require that both tasks be completed simultaneously. They simply require that the first task be finished, in order for the second task to finish. The second task can finish any time after the first task finishes. In our wedding cake example, let's say there are some finishing touches to the decorations that you can't finish until the cake is delivered. You can use a finish-to-finish dependency between the "Decorate cake" and "Deliver cake" tasks. When the "Decorate cake" task is finished, then the "Deliver cake" task can be completed.

FF

Finally, the start-to-finish (SF) dependency is a little tricky. When you use this type of dependency, you are saying that the second task in the relationship can't finish until the first task starts. However, the second task can finish any time after the first task starts. Going back to our wedding cake example, let's say you have a task for billing the customer. It begins when the customer requests the cake, but it can't be completed until after the cake delivery has begun. You can use a start-to-finish dependency between the "Deliver cake" and "Bill customer" tasks, so that when the "Deliver cake" task has begun, it is okay for the "Bill customer" task to finish.

SF

So when you put the entire plan together, with these dependencies intact, the plan might look something like this:

AllLinks

How do I create dependencies?

First, you need to determine whether you want to create a dependency between two tasks in the same project, or between a task in one project and a task in another project.

If you want to create a dependency between two tasks in the same project, review Create task dependencies (links) within your project.

If you want to create a dependency between a task in one project and a task in another project, review Create task dependencies (links) across projects.

Where can I learn more?

Learn more about task dependencies in the following articles:

· View and update task dependencies (links) across projects

· Create and link tasks with Project 2007

· Watch this: Create a cross-project link

· Watch this: Link tasks in your project

· Change or remove task dependencies (links)