Material Resource Usage Illustrated


Dr. Ed Hanna, one of our most senior field people for EPM recently posted a great example of using material resources using Project Server.  So, I’m taking Ed’s e-mail and converting into this post.  I hope you find this very useful.

Here’s an example of how you might use Project to track the pouring of the concrete for one section of a dam.

First, create a Resource Sheet entry for the concrete.  Click the image below for more detail.

The dam footing work we are tracking will contain 20,000 cu. meters of concrete and will be poured over a ten workday period.  The Gantt Chart task to pour this footing looks as follows.

Next, the Resource Usage view shows the planned usage of concrete at 2,000 cu. meters per day. Note: there is no Actual Work as the task has not yet begun.

Once progress begins, the Resource Usage view can be used to report actual usage.  In this case, only 1,000 cu. meters of concrete poured on day #1.  Consequently, work is off to a slow start.

Here’s the full Resource Usage view showing 3,000 cu. meters of additional concrete poured on day #2.  On the left you can see totals.  For example, you can see that 20,000 cu. meters of concrete is scheduled to be poured (i.e. Work) and so far 4,000 cu. meters have been poured (i.e. Actual Work). The graph in the lower portion of the display shows Cumulative Scheduled Work (i.e. the cumulative amount of concrete scheduled to be poured).

The display can also be changed to track the cost of the concrete. The graph in the lower portion of the display shows Cumulative Scheduled Cost (i.e. the cumulative cost of concrete scheduled to be poured).

I hope this is helpful.  By the way, Hoover Dam contains 3.33M cu. meters of concrete. 

 

Comments (20)

  1. Danielle says:

    How can I change a date and everything follows (date change)

  2. Mc Kenzie says:

    Please inform me if some one can put

    Engineer,Foreman,Labour, Equipment, Material, and also the cost breakdown, any body can help thanks My e-mail>>> Khadafi_97@yahoo.co.id

  3. wellbutrin says:

    <a href= http://zocorprices.jconserv.net/ >zocor withdrawal effect</a>  http://acyclovirsi.phpbb3.com/ acyclovir to treat flu  

  4. doxycycline says:

    <a href= http://whatisamoxicillin.blog.hr/ >dug interactions amoxicillin</a>  http://whatisativan.blogyx.com/ ativan dose  

  5. cephalexin says:

    <a href= http://whatisativan.blogyx.com/ >buy ativan on line</a>  http://blogs.skaffe.com/withcodeine/ codeine dosage limitations  

  6. altace says:

    <a href= http://codeinesy.diaryland.com/ >robutussen with codeine</a>  http://diazepamsideeffects.alkablog.com/ diazepam overnight  

  7. Jose says:

    It is very useful.

    My concern is about the stock. Is it possible to have this functionality? I suppose you know what I mean. The system could track the amount of material available. If you don’t have enough you could have a “overallocation” problem like working with a human resource.

  8. You could do this through custom fields. Add a custom resource number field which would store the number of stock you have. Then you could compare this to the work field which shows the current number of units you plan to use for that material resource. You could even add another custom field that would use a graphical indicator that would turn red when work is greater than stock.

    Thanks.

  9. Jack says:

    I am trying this example but I am not getting same results as shown in the article. Can some one upload or provide link to download MPP file that shows this example? It will be great help..

    Regards

    Jack

  10. Toneys says:

    Here's a video on material resources

  11. Henry says:

    Thanks for your very useful topic. May i ask you if we could add or create another fields of usage details in Detail Styles section ?

    regards

    henry

  12. KISHORE says:

    ONE OF THE BEST BLOGS SHOWING RESOURCES CONCEPT IN MS PROJECT FOR BEGINNERS

Skip to main content