Synchronizing the Schedule Information between PS 2007 and PPS 2007

 

One of the common query that I have seen is how to synchronize the schedule information between Project Server and Portfolio Server.

 

Ideally once you setup and Project Server  Gateway and export the project to Project Server 2007 - things should work seamless.  Indeed it does with small catch that sometime you might notice that "% Complete" is not updated after synchronization.

 

Solution is to ensure that in the current workflow stage you have the "Lock Business Case ( Post-approval) check box checked.