Sprint 4 ending (mostly) happily

Well, my dear readers, I’m pleased to report that we got things pulled together for sprint 4 and are on track to complete it successfully today, barring unforeseen complications.   One of the problems we’ve had is that our overarching mission timeline is basically impossible, and most of us on the effort have known it,…

0

Continued use of Scrum

Dear Readers –   We continue to use Scrum on our project, and we’re now finishing our third sprint (numbered sprint 4 to match up with pre-Scrum milestone numbering).   It’s been a stressful sprint.  We had a bunch of very hard changes which took much longer than we expected, and this week it became…